top button
Flag Notify
    Connect to us
      Site Registration

Site Registration

X can do a piece of work in 25 days and Y is 25% more efficient than X. How many days Y will take to finish the work?

0 votes
658 views
X can do a piece of work in 25 days and Y is 25% more efficient than X. How many days Y will take to finish the work?
posted Mar 5, 2016 by anonymous

Share this puzzle
Facebook Share Button Twitter Share Button LinkedIn Share Button

1 Answer

0 votes

25 / 1.25 = 20 days

answer Mar 7, 2016 by Jcm



Similar Puzzles
0 votes

B is more efficient than A and they together can complete a work in 18 days.
Had A done 60% of the work and then B, the remaining work, then the work would have been completed in 39 days.
B alone will complete 60% of the same work in how many days?

0 votes

C with his 200% efficiency, can complete 25% of a certain work in 12 days.
B is 20% more efficient than C.
A with 75% efficiency can complete the work in same days as B.
If A and B together finish the same work and A gets Rs. 10400, then what is the share of B?

0 votes

Vinay can do a certain work in 16 days.
Shubham is 60% more efficient than Vinay.
How many days does Shubham alone take to do the same work?

0 votes

A alone can complete a piece of work in 30 days.
B is 50% more efficient than A.
With the help of C, together they completes the work in 6 days, then C is ____ efficient than ______.
Fill in the blanks.

0 votes

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

...