How many days will take for A, B and C combined together to complete the same amount of work?

0 votes
202 views

A and B can complete a work in 12 days. B and C can complete the same work in 18 days. C and A can complete in 24 days. How many days will take for A, B and C combined together to complete the same amount of work?

posted Jul 9, 2014 by anonymous

Share this puzzle
Facebook Share Button Twitter Share Button Google+ Share Button LinkedIn Share Button Multiple Social Share Button

2 Solutions

+3 votes

1/a+1/b = 1/12
1/b+1/c = 1/18
1/c+1/a = 1/24

so
2(1/a+1/b+1/c) = (6+4+3)/72
or 1/a+1/b+1/c = 13/(2*72)

or A , B and C together can finish in 144/13 or 11.1 days.

solution Jan 30, 2015 by Nikhil Pandey
–1 vote

a+b=12
b+c=18
c+a=24
a+b+c=(12+18+24)/2
= 27

solution Jan 30, 2015 by @@@@@@@@@@@@@
Sir check if a and b are finishing in 12 days the a b and c should be less then 12 :)



Similar Puzzles
0 votes

P is able to do a piece of work in 15 days and Q can do the same work in 10 days. If they can work together for 2 days, what is the fraction of work left?

0 votes

If 15 men take 21 days of 8 hours each to do a piece of work. How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men?

0 votes

A forms a wall in 10 days and B forms it in 15 days. A and B start the work of forming wall together but after 2 days A leaves the work. How many days are required for making the remaining wall by B?

Contact Us
+91 9880187415
sales@queryhome.net
support@queryhome.net
#470/147, 3rd Floor, 5th Main,
HSR Layout Sector 7,
Bangalore - 560102,
Karnataka INDIA.
QUERY HOME
...