How many days are required to do the same work with a working of 6 hours per day ?

0 votes
444 views

12 labours construct 120 toys in 8 days working 8 hours per day .
If two them leave the work , then how many days are required to do the same work with a working of 6 hours per day ?

posted Nov 4, 2014 by Balwinder

Share this puzzle
Facebook Share Button Twitter Share Button Google+ Share Button LinkedIn Share Button Multiple Social Share Button

2 Solutions

0 votes

13.80 days...

solution Nov 4, 2014 by Kshitij Maloo
What is the logic on how you reach to the solution
By the way you are a good puzzler just be more descriptive in your answers and you can ask puzzles also ha ha ha
0 votes

12.8 days or 12 days + 4 hours 48 mins on 13th day.
Total labour hours required for 120 toys = 12*8*8 = 768 labour hours
With 10 labourers and 6 hours a day of wrok,
labour hours available = 10*6 = 60 labour hours
No.of days required with 60 labour hours per day = 768/60 = 12.8

solution Dec 17, 2015 by anonymous



Similar Puzzles
0 votes

Six men do a piece of work in 10 days with an effort of 6 hours per day. How many extra men are required for doing the work of double strength in 4 days with an effort of 5 hours per day

+1 vote

If A men working A hours a day can do A units of a work in A days, then how many units of work can be completed by B men working B hours per day.

0 votes

3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?

+1 vote

If 9 boy working 15/2 hours a day can finish a work in 20 days, then how many days will be taken by 12 boy working 6 hours a day to finish the work, it being given than 3 boy of latter type work as much as 2 boy of he former type in the same.

0 votes

If 15 men take 21 days of 8 hours each to do a piece of work. How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men?